The painters are ahead of schedule. Hooray. They have painted the inside ceilings, exposed air ducts and now that things have dried up outside are tackling the roof and areas of the building that aren’t waiting to be reconstructed. Commonweath Electric company sent a crew in today to rough out the locations of lights and switches in the new walls that we built inside. First you frame the walls, then run electric and low voltage data wiring, then get an inspection for framing and electric, then drywall, then wainscot, then paint high walls, then stain and varnish wainscot, then faux paint walls. The electrician decision was holding us up but this crew is on it and we should be ready for inspection by Thursday. We’re also pouring concrete in the back of the building tomorrow morning for a utility room. Another rain delayed project to get us back on track. The pictures show one perspective of the roof being painted and my daughter Jenny helping me with a roof inspection. Extra credit if you can find and ID the hidden three people
in the first photo.